How To Calculate Quantity Of Soil/Sand For Filling Plots
Soil filling is one of
the essential features required for every construction projects. So that
the site gets developed and prepared for construction. In this article, We
will discuss how to calculate the quantity of soil/sand and no. of trally/tucks
required for filling plot.
Let,
Length of the plot = 50
feet.
Width of the plot = 40
feet.
Area of the plot = Length
x Width = 50 x 40 =2000 sft.
Suppose we need to fill
the plot by 3’5” = 3.41 feet.
∴ Depth of the plot = 3.41 feet.
Volume of plot to be
filled = 2000 x 3.41 = 6820 cft.
This volume is for loose
state.
For full compacted state,
required quantity of soil/sand for filling the plot = 6820 x 1.30 = 8866 cft (1.30 is factor)
Now we will calculate
required no of trally/ trucks.
Suppose a trally can
carry 70 cft soil.
∴ No. of trally rerquired = 8866/70 = 126.65 = 127 no. of trally.
Suppose a truck can carry
500 cft.
Comments
Post a Comment