Who to Calculate the Quantity of Cement and Sand in Plaster
How to calculate cement, sand quantity for
Plastering?
Before beginning to
work on the plastering calculation, note down these general things
·
Cement Mortar Ratio for wall plastering 1:6
·
Cement Mortar Ratio for ceiling plastering
1:4
·
Plastering thickness should not be more
than 12-15 mm. If there is a need for an additional coat don’t do that at
one go.
·
Ensure you are using good quality of cement
& Sand (In silt content test, we have discussed how bad sand quality
affects the work)
·
Also, ensure you are using measuring box
(not head pan) for site mix ( Here is the basic construction tools list)
·
Please do read the plastering
checklist post for the complete list.
Plastering Work Ratio Calculation
For a better
understanding, we are going to do this calculation for 100 Sq.m area.
To calculate the cement and sand for 100 m2 plastering
area in 1:6 ratio and 12 mm thickness.
Cement Mortar Required:
Volume of cement
mortar required = ( Plastering Area x thickness )
= 100 m2 x 0.012m
= 1.2 m3
(This is wet volume
that means we need this much volume of cement mortar after mixing water, So for
dry volume, we have to add 30-35% as bulkage of sand, we are using 35% and
wastage as 20%)
Consider 35% Sand Bulkage = 1.2 m3 x
(1+0.2+0.35) (Many of us would use 1.54 as constant)
= 1.86 m3
Cement : Sand (Ratio) = 1 : 6 ( Total = 1+6 = 7
Parts )
Cement required (1 Part) = 1.86 x 1/7
= 0.265 m3 /0.0347
= 7.66 bags (Approx – 8 Bags)
Sand required (5 Part) = 1.86 x 6/7
= 1.59 m3